Question: A local project being analyzed by PERT has 10 activities, 7 of which are on the critical path. If the estimated time along the critical

  1. A local project being analyzed by PERT has 10 activities, 7 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 110 days or less? (please answer to four decimal digits)

2. The following represents a project with known activity times. All times are in weeks.

Activity

Immediate

Predecessor

Time

(weeks)

A - 5
B - 3
C A 5
D B 5
E C, D 1
F B 5

What is the minimum possible time required for completing the project (round it to the nearest whole number)?

3. The following represents a project with four activities. All times are in weeks.

Activity

Immediate

Predecessor

Optimistic

Time

Most

Likely

Time

Pessimistic

Time

A - 2 8 14
B - 8 8 8
C A 6 9 18
D B 2 11 17

What is the minimum expected completion time for the project (please round off to two decimal digits)?

Your Answer:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock