Question: A local project being analyzed by PERT has 10 activities, 7 of which are on the critical path. If the estimated time along the critical
- A local project being analyzed by PERT has 10 activities, 7 of which are on the critical path. If the estimated time along the critical path is 105 days with a project variance of 25, what is the probability that the project will be completed in 110 days or less? (please answer to four decimal digits)
2. The following represents a project with known activity times. All times are in weeks.
| Activity | Immediate Predecessor | Time (weeks) |
| A | - | 5 |
| B | - | 3 |
| C | A | 5 |
| D | B | 5 |
| E | C, D | 1 |
| F | B | 5 |
What is the minimum possible time required for completing the project (round it to the nearest whole number)?
3. The following represents a project with four activities. All times are in weeks.
| Activity | Immediate Predecessor | Optimistic Time | Most Likely Time | Pessimistic Time |
| A | - | 2 | 8 | 14 |
| B | - | 8 | 8 | 8 |
| C | A | 6 | 9 | 18 |
| D | B | 2 | 11 | 17 |
What is the minimum expected completion time for the project (please round off to two decimal digits)?
Your Answer:
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
