Question: A machine shop produces the mechanical component A which consists of the sub-componentsB, C, D, as follows: For every A component that is ordered/produced, three
A machine shop produces the mechanical component A which consists of the sub-componentsB, C, D, as follows: For every A component that is ordered/produced, three B sub-componentsand two C sub-components are needed. Furthermore, for each C sub-component, two B sub-components and four D sub-component are needed. The following information is known
| Inventory Level | Lead Time | Safety Inventory Level | Lot size | |
| A | 138 | 2 | 36 | 24 |
| B | 204 | 2 | 20 | 50 |
| C | 223 | 1 | 120 | 15 |
| D | 527 | 4 | 10 | 1 |
The gross demand for A for the next six months is given in the table below
| Month | 1 | 2 | 3 | 4 | 5 | 6 |
| Gross Requirements | 17 | 19 | 6 | 14 | 50 | 58 |
Fill the MRP table for sub-component B
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock