Question: A manager decides to design a production line for a job with 3 tasks. The task times are 0 . 5 minutes, 1 . 4

A manager decides to design a production line for a job with 3 tasks. The task times are 0.5 minutes, 1.4 minutes, and 0.7 minutes. What is the cycle time in minutes, for a single production line with no parallel activities?
1.4
0.5
2.6
0.7