Question: A manager must decide between two machines. The manager will take into account each machine's operating costs and initial costs, and its breakdown and repair


A manager must decide between two machines. The manager will take into account each machine's operating costs and initial costs, and its breakdown and repair times. MachineA has a projected average operating time of128 hours and a projected average repair time of 7' hours. Projected times for machine B are an average operating time of 58 hours and a repair time of 6 hours. What are the projected availabilities of each machine? {Round your answers to 3 decimal places.)