Question: A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 33 units. Assume the shop works a
A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 33 units. Assume the shop works a 60-minute hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules:
1. In order of most following tasks. Tiebreaker: greatest positional weight.
| Station | Tasks assigned | Total time at station | Idle time at station |
| 1 | |||
| 2 | |||
| 3 | |||
| 4 |
2. In order of greatest positional weight. Tiebreaker: most following tasks.
| Station | Tasks assigned | Total time at station | Idle time at station |
| 1 | |||
| 2 | |||
| 3 | |||
| 4 |
3. What is the efficiency?
efficiency is % (two decimal places)