Question: A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 331/3 units. Assume the shop works a
A manager wants to assign tasks to workstations as efficiently as possible and achieve an hourly output of 331/3 units. Assume the shop works a 60-minute hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules:
.png)
a. In order of most following tasks. Tiebreaker: greatest positional weight.
b. In order of greatest positional weight. Tiebreaker: most following tasks.
c. What is theefficiency?
Step by Step Solution
There are 3 Steps involved in it
Given Desiredoutput rate 33 13 units per hour Operating time 60 minutes per hour We aregiven the tasks and their times in minutes shown below a Use the most following tasks heuristic andin the case of ... View full answer