Question: A manager wants to build 3 - sigma x - bar control limits for a process. The target value for the mean of the process

A manager wants to build 3-sigma x-bar control limits for a process. The target value for the mean of the process is 10 units, and the standard deviation of the process is 6. If samples of size 9 are to be taken, what will be the upper and lower control limits, respectively?
Group of answer choices
16 and 4
-8 and 28
12 and 8
4 and 16
8 and 12