Question: A manager wants to build 99.7% control limits for a process. The target value for the mean of the process is 10 units, and the

A manager wants to build 99.7% control limits for a process. The target value for the mean of the process is 10 units, and the standard deviation of the process is 6. If samples of size 9 are to be taken,

a) What is the UCL (Upper Control Limit)

b) What is the UCL (Lower Control Limit)