Question: A manual assembly line is to be designed to make a small consumer product. The work elements, their times, and precedence constraints are given in

A manual assembly line is to be designed to make a small consumer product. The work elements, their times, and
precedence constraints are given in the table below. The workers will operate the line for 420 min per day and must
produce 300 products per day. A mechanized belt, moving at a speed of 1.25 m/min, will transport the products between
stations. Previous experience suggeststhat the up time efficiency for the line will be 95%, and repositioning time lost
per cycle will be 0.03 min.
a) Detennine the theoretical minimum number of workers on the line. [2]
b) Balance the line using the rank positional weight method and calculate its efficiency. [12)
Element Time(Min.) Preceded by Element Time Preceded by
0.460.23
20.770.34
30.580.94,9
40.8290.35,6
51.02,3100.57,8

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!