Question: Question 2 A manual assembly line is to be designed to make a small consumer product. The work elements, their times, and precedence constraints are

Question 2
A manual assembly line is to be designed to make a small consumer product. The work
elements, their times, and precedence constraints are given in the table below. The workers
will operate the line for 400 min per day and must produce 300 products per day. A
mechanized belt, moving at a speed of 1.25 m/min, will transport the products between
stations. Because of the variability in the time required to perform the assembly operations,
it has been determined that the tolerance time should be 1.5 times the cycle time of the line.
2.1.1 Construct the precedence diagram (10)
2.1.2 Determine the ideal minimum number of workers (1)
2.1.3 Use the Largest Candidate Rule method to balance the line. (10)
2.1.4 Compute the balance delay for your solution in 1.1.3.(2)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!