Question: A manual assembly line is to be designed to make a small consumer product. The work elements, their times, and the precedence constraints are given

A manual assembly line is to be designed to make a small consumer product. The work elements, their times, and the precedence constraints are given in the table below.
\table[[Element,Time (min),Preceded by],[1,0.4,-],[2,0.7,1],[3,0.5,1],[4,0.8,2],[5,1.0,2,3],[6,0.2,3],[7,0.3,4],[8,0.9,4,9],[9,0.3,5,6],[10,0.5,7,8]]
Tc=5.6
The workers will operate the line for 400min per day, and must produce 300 products per day. A mechanized belt, moving at a speed of 1.25mmin will transport the products between stations. Because of the variability in the time required to perform the assembly operations, it has been determined that the tolerance time should be 1.5 times the cycle time of the line.
(a) Determine the ideal minimum number of workstations on the line.
(b)(i) Use the Largest Candidate Rule method to balance the line.
(ii) Use the Ranked Positional Weight method to balance the line.
(c) Calculate the balance delay for your solution in part (b)(i) & (b)(ii).
(d)Determine the spacing between assemblies on the line.
(e) the required length of each workstation to meet the specifications of the line.
 A manual assembly line is to be designed to make a

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!