A manufacturer of baseball controls material flow by using a Kanban system. The balls are transported to
Fantastic news! We've Found the answer you've been seeking!
Question:
A manufacturer of baseball controls material flow by using a Kanban system. The balls are transported to the final operation, Cover Sewing, in a transport bin that contains (35) baseballs. The Cover Sewing operation produces 15 baseballs per hour. It takes about five hours to replenish the transport bin. There is a high level of turnover in the Cover Sewing department, so management has decided to keep a safety stock of 18%. How many kanban card sets are required for this process?