Question: A manufacturing cell within a value stream is structured with four processes. The processes and their associated unit processing times are as follows: Cutting 12

A manufacturing cell within a value stream is structured with four processes. The processes and their associated unit processing times are as follows: 

Cutting 12 minutes 

Drilling and insertion 8 minutes 

Assembly 12 minutes

Finishing 9 minutes 

Calculate the number of units the cell can produce per hour on a continuous running basis (production rate).


Step by Step Solution

3.37 Rating (156 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

Overall processing time for a single unit sum of the individual procedure processing times Cutting ... View full answer