Question: A manufacturing company produces widgets using two production processes: Process A and Process B . Process A has a production capacity of 5 0 0

A manufacturing company produces widgets using two production processes: Process A and Process B. Process A has a production capacity of 500 widgets per hour, while Process B has a capacity of 700 widgets per hour. The company operates 8 hours per day. Calculate the total daily production capacity for each process, and determine the bottleneck process. Additionally, discuss the implications of the bottleneck on production scheduling and overall efficiency.