Question: Question: A manufacturing company produces widgets using two processes: Process A and Process B . Process A has a daily capacity of 5 0 0

Question:
A manufacturing company produces widgets using two processes: Process A and Process B. Process A has a daily capacity of 500 units, while Process B has a daily capacity of 700 units. The company operates 8 hours per day. If Process A takes 30 minutes to produce one unit, and Process B takes 20 minutes per unit, determine:
a) The total daily production capacity of each process.
b) Which process is the bottleneck.
c) The maximum number of units produced per day.