Question: A manufacturing process has 2 stations, A and B, that are ordered in sequence. At each station, two tasks are performed one after the other.
A manufacturing process has 2 stations, A and B, that are ordered in sequence. At each station, two tasks are performed one after the other. Suppose the time (in seconds per unit) it takes for a single person to perform each task is as given in the table below:
(e.g., task A2 takes 25 seconds per unit). If station A has 1 worker and station B has two workers to do the different tasks, what is the capacity of this process under steady state (in units per hr)?
| STATION | # OF WORKERS | TASK A1 | TASK A2 | TASK B1 | TASK B2 |
|---|---|---|---|---|---|
| A | 1 | 20 | 25 | - | - |
| B | 2 | - | - | 40 | 40 |