Question: A manufacturing project has a schedule performance index ( SPI ) of 0 . 8 9 and a cost performance index ( CPI ) of

A manufacturing project has a schedule performance index (SPI) of 0.89 and a cost performance index (CPI) of 0.91. Generally, what is the most likely explanation for why this occurred?a.A critical path activity took longer and needed more labor hours to complete.b.The scope was changed.c.Additional equipment needed to be purchased.d.A supplier went out of business, and a new one needed to be found.