Question: As a project manager, you have submitted a change request to the Change Control Board ( CCB ) . The CCB has reviewed and approved

As a project manager, you have submitted a change request to the Change Control Board (CCB). The CCB has reviewed and approved the change. Which of the following project performance indicators may have been the reason for initiating the change request?
A Schedule Performance Index (SPI) of 1.3 and Cost Performance Index (CPI) of 1.2
B Schedule Performance Index (SPI) of 1.0 and Cost Performance Index (CPI) of 1.0
C Schedule Performance Index (SPI) of 1.7 and Cost Performance Index (CPI) of 1.1
D Schedule Performance Index (SPI) of 0.6 and Cost Performance Index (CPI) of 0.8
 As a project manager, you have submitted a change request to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!