Question: A manufacturing system is designing a product layout for a new product. They plan to use this production line ten hours a day in order

A manufacturing system is designing a product layout for a new product. They plan to use this production line ten hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product:
TASK PREDECESSOR TIME(seconds)
A 34
B A 20
C B 10
D B 16
E C 10
F D, E 24
G F 38
For output to equal forecasted demand, what will be the second task performed at the second workstation of the production line that uses the minimum number of stations? Hint: Use the heuristic rule "Assign the task with the most followers."
Balancing Formula
Multiple Choice
E
A
B
C
D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!