Question: A manulacturing system is designing a product layout for a new product. They plan to use this production line ten hours a day in order

A manulacturing system is designing a product
A manulacturing system is designing a product layout for a new product. They plan to use this production line ten hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: What cycle time will provide an output rate of 900 units per day? a. 32 seconds b. 38 seconds: c. 40 seconds d. 76 seconds e. 152 seconds Clear my choice