Question: A marketing team has been given a group writing assignment. The deadline is three months away. When should the group start working on the project?
A marketing team has been given a group writing assignment. The deadline is three months away. When should the group start working on the project?
Multiple Choice
in a month
a week before the deadline
immediately
two weeks before the deadline
in two weeks