Question: A master production schedule ( MPS ) is a statement of _ _ _ _ _ _ _ _ _ _ Select one: a .

A master production schedule (MPS) is a statement of __________
Select one:
a.
what is the supply for an item derived from all of its children.
b.
how many items are in the orders and when the orders will be received.
c.
what is the demand for an item derived from all of its parents.
d.
how many orders are due or planned to be delivered.
e.
how many finished items are to be produced and when they are to be produced.