Question: A medium - size municipality plans to develop asoftware system to assist in project selection dur - ing the next 1 0 years. A life

A medium-size municipality plans to develop asoftware system to assist in project selection dur-ing the next 10 years. A life-cycle cost approachhas been used to categorize costs into develop-ment, programming, operating, and support costsfor each alternative. There are three alternativesunder consideration, identified as A (tailored sys-tem), B (adapted system), and C (current system).Use an annual life-cycle cost approach to identifythe best alternative at 8% per year.