Question: A methods and measurements analyst for Timepiece, Inc., needs to develop a time standard for the task of attaching a watch to a wristband. In
A methods and measurements analyst for Timepiece, Inc., needs to develop a time standard for the task of attaching a watch to a wristband. In a preliminary study, he observed one of his workers perform this task five times, with the following results:
| Observation | 1 | 2 | 3 | 4 | 5 |
| Time (secs) | 27 | 19 | 20 | 21 | 13 |
What is the standard time for this task if the employee worked at a 20 percent faster pace than average, and an allowance of 20 percent of the workday is used?
-
20 seconds
-
24 seconds
-
25 seconds
-
28.8 seconds
-
30 seconds
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock