Question: A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers

 A methods and measurements analyst needs to develop a time standard

A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers perform this task five times, with the following results: What is the standard time for this task if the employee worked at a 20 percent slower pace than average and an allowance of 30 percent of the workday is used? 125 seconds 66 seconds 94 seconds: 82 seconds 100 scconds