Question: A Methods and Measurements Analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his employees

A Methods and Measurements Analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his employees perform this task five times, with the following results:OBSERVATION12345TIME (SECONDS)8476808476What is the standard time (ST) for this task if the employee worked at a twenty-five percent faster pace than the average and an allowance of twenty percent of the workday is used? Select one:a.125 secondsb.100 secondsc.80 secondsd.120