Question: A methods and measurements analyst needs to develop a time standard for a certain tisk. In a preliminary study, he observed one of his workers

A methods and measurements analyst needs to

A methods and measurements analyst needs to develop a time standard for a certain tisk. In a preliminary study, he observed one of his workers perform this task live times with the following results Observation 3 + S Time (seconds) 84 76 80 84 76 What is the standard time for this take the employee worked at a 25 percet fer patham vereind allowance of 20 percent of the workday is used One