Question: A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers
A methods and measurements analyst needs to develop a time standard for a certain task. In a preliminary study, he observed one of his workers perform this task five times, with the following results: Observation 1 2 3 4 5 Time (secs) 85 83 80 76 84 What is the standard time for this task if the employee worked at a 27 percent slower pace than average and an allowance of 21 percent of the job time is used? (Keep one decimal place in your answer)