A milestone is a typical measuring point used when establishing cost control. Which of the following does NOT accurately describes the use of cost control milestones?
a Project managers can use their cash flow projections to determine the funding needed to reach each milestone.
b Project managers and sponsors often decide the number of milestones jointly.
c Milestones are often identified in the project charter.
d Milestones are developed during risk planning.