Question: When establishing cost control, a milestone is a typical measuring point. Which of the following does NOT accurately describes the use of cost control milestones?
When establishing cost control, a milestone is a typical measuring point. Which of the following does NOT accurately describes the use of cost control milestones?
a
Project managers can use their cash flow projections to determine the funding needed to reach each milestone.
b
Major milestones are often identified in the project charter.
c
Milestones are developed during risk planning.
d
Project managers and sponsors often decide how many milestones to use.