Question: A milling machine requires four setups per production cycle. Each setup takes 25 minutes. The processing time is 0.6 minute per unit. What batch size
A milling machine requires four setups per production cycle. Each setup takes 25 minutes. The processing time is 0.6 minute per unit. What batch size (rounded to the nearest whole number) will achieve a capacity of 50 units per hour