Question: A mining company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t=0 of $13.5 million. Under Plan A,
A mining company must choose between two mutually exclusive extraction projects, and each requires an initial outlay at t=0 of $13.5 million. Under Plan A, all the oil would be extracted in 1 year, producing a cash flow at t+1 of $19.8 million. Under Plan B, cash flows would be $3.8 million per year for 9 years. Estimate the crossover rate of the NPVs for Plans A and B. If the firms WACC is 15% what is the NPV of the project you would recommend?
Group of answer choices
16.97% ; $4.63 million
12.12% ; $3.72 million
14.60%; $3.72 million
12.26% ; $5.52 million
12.12%; $4.63 million