Question: A Moving to another question will save this response. Question 17 A network consists of the activities in the following list. Times are given in

A Moving to another question will save this
A Moving to another question will save this response. Question 17 A network consists of the activities in the following list. Times are given in weeks. Preceding Activity A B D Time 8 3 7 3 A A,B What is the EF of activity D? 8 3 3 None of the above