Question: A network has only one critical path and the slack for noncritical activities is high. This network would appear to have a _ _ _

A network has only one critical path and the slack for noncritical activities is high. This network would appear to have a _______ level of sensitivity
Group of answer choices
moderate
high
extreme
low
very high