Question: A. Network Information Chart (NIC) TABLE B. Project Network Diagram (AON), From the NIC table C . graphically display the project, start/end dates and identify

A. Network Information Chart (NIC) TABLE

B. Project Network Diagram (AON), From the NIC table

C. graphically display the project, start/end dates and identify the Critical Path of the project. Both the Forward and Backward pass will be required to calculate slack and identify the Critical Path

Project duration is 30 days

TASK

Time

START DATE

Complete Date

A

1 day

May 1, 2022

May 1, 2022

B

3 days

May 2, 2022

May 4, 2022

C

1 day

May 5, 2022

May 5,2022

D

1 day

May 6, 2022

May 6,2022

E

3 days

May 7, 2022

May 9, 2022

F

2 days

May 10, 2022

May 11, 2022

G

2 days

May 12,2022

May 13,2022

H

2 days

May 14, 2022

May 15,2022

I

2 days

May 16, 2022

May 17,2022

J

2 days

May 18,2022

May 19,2022

K

1 day

May 20,2022

May 20,2022

L

2 days

May 21,2022

May 22,2022

M

1 days

May 23,2022

May 23,2022

N

4 days

May 24,2022

May 27,2022

O

1 day

May 28,2022

May 28,2022

Q

1 day

May 29,2022

May 29,2022

R

1 day

May 30,2022

May 30,2022

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!