Question: A. Network Information Chart (NIC) TABLE B. Project Network Diagram (AON), From the NIC table C . graphically display the project, start/end dates and identify
A. Network Information Chart (NIC) TABLE
B. Project Network Diagram (AON), From the NIC table
C. graphically display the project, start/end dates and identify the Critical Path of the project. Both the Forward and Backward pass will be required to calculate slack and identify the Critical Path
Project duration is 30 days
| TASK | Time | START DATE | Complete Date |
| A | 1 day | May 1, 2022 | May 1, 2022 |
| B | 3 days | May 2, 2022 | May 4, 2022 |
| C | 1 day | May 5, 2022 | May 5,2022 |
| D | 1 day | May 6, 2022 | May 6,2022 |
| E | 3 days | May 7, 2022 | May 9, 2022 |
| F | 2 days | May 10, 2022 | May 11, 2022 |
| G | 2 days | May 12,2022 | May 13,2022 |
| H | 2 days | May 14, 2022 | May 15,2022 |
| I | 2 days | May 16, 2022 | May 17,2022 |
| J | 2 days | May 18,2022 | May 19,2022 |
| K | 1 day | May 20,2022 | May 20,2022 |
| L | 2 days | May 21,2022 | May 22,2022 |
| M | 1 days | May 23,2022 | May 23,2022 |
| N | 4 days | May 24,2022 | May 27,2022 |
| O | 1 day | May 28,2022 | May 28,2022 |
| Q | 1 day | May 29,2022 | May 29,2022 |
| R | 1 day | May 30,2022 | May 30,2022 |