Question: A new engineering team is put together for the development of a new product. This new product will be built through an assembly line. The

A new engineering team is put together for the development of a new product. This new product will be built through an assembly line. The production manager designs the assembly line. He has been advised that the assembly line must be ready in four weeks (20 working days) for a test run. The manager decided to use CPM (critical path method) and has broken down the projects into the following activities, determined their precedence relationships, and estimated normal times:

Activity

Immediate Predecessors

Normal Time (days)

Crash Time (days)

Crashing Cost ($/ day)

a. organize layout team

none

5

5

-

b. organize modification team

none

3

3

-

c. design personnel jobs

a, b

2

1

500

d. set machinery in place

none

3

1

2500

e. connect utilities

d

3

2

1000

f. modify conveyor system

c, e

4

3

1200

g. train personnel

c

3

3

-

h. finishing touches

f, g

5

3

800

i. run test lot

h

2

2

-

Based on the information provided above, answer the following questions.

1. What is the project earliest completion time in days? Round your answer to the nearest integer. Your answer is ____. (1 point)

2. The manager would like to expedite the project by 1 day. According to the crashing data provided in the table, which task should be expedited? Input the task label here. For example, if your answer is a organizing layout team, input a. Your answer is ____. (1 point)

3. What is the EST of activity g? Round your answer to the nearest integer. Your answer is ____. (1 point)

4. What is the LST of activity c? Round your answer to the nearest integer. Your answer is ____. (1 point)

5. What is the LST of activity g? Round your answer to the nearest integer. Your answer is ____. (1 point)

6. What is the slack time of activity g? Round your answer to the nearest integer. Your answer is ____. (1 point)

7. How many critical tasks are on the critical path (excluding S and T)? Round your answer to the nearest integer. Your answer is ____. (1 point)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!