Question: A new microprocessor was designed and tested for performance. This microprocessor requires 2 , 5 or 6 machine cycles to perform various operations. 4 5

A new microprocessor was designed and tested for performance. This microprocessor requires 2,5 or 6 machine cycles to perform various operations. 45% of its instructions take 2 machine cycles,
40% take 5 machine cycles and 15% take 6 machine cycles.
a) Compute the average CPI for the microprocessor. [1 Mark ]
b) What is the clock frequency required for the CPU to be at 500 MIPS? [2'Marks]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!