Question: Q 1 : Answer the following questions. A ) A new microprocessor was designed and tested for performance. This microprocessor requires 2 , 5 or

Q1: Answer the following questions.
A) A new microprocessor was designed and tested for performance. This microprocessor requires 2,
5 or 6 machine cycles to perform various operations. 45% of its instructions take 2 machine cycles,
40% take 5 machine cycles and 15% take 6 machine cycles.
a) Compute the average CPI for the microprocessor. [1 Mark]
b) What is the clock frequency required for the CPU to be at 500 MIPS? [2 Marks]
 Q1: Answer the following questions. A) A new microprocessor was designed