Question: A new project includes outsourced work and has been going badly. The project deliverables have changed three times, the functional managers keep removing people from

A new project includes outsourced work and has been going badly. The project deliverables have changed three times, the functional managers keep removing people from the team, and the project schedule baseline has been adjusted four times in the first week. What could be done to prevent these issues from occurring again? ... A. B. C. D. Create a resource management plan. Create a scope management plan. Create a signed project charter. Obtain clear direction from the sponsor