Question: A new project manager has been brought in to replace the prior PM who just retired from a long and distinguished career. Eager to make
A new project manager has been brought in to replace the prior PM who just retired from a long and distinguished career. Eager to make a good
impression and to fill the shoes of such a highperformer, the new PM asks to see the scope baseline for the project so that she can immediately begin to
control scope creep. What is included in the scope baseline?
A Scope management plan, project scope statement, WBS and WBS dictionary
B Project scope statement, WBS and WBS dictionary, planning package
C Scope management plan, and project scope statement
D WBS and WBS dictionary
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock