Question: A new school is being constructed using the NEC 4 Engineering and Construction Contract Option A with secondary Options X 7 , X 8 ,
A new school is being constructed using the NEC
Engineering and Construction Contract Option A with secondary Options X
X
X
and X
No programme is identified in the Contract Data and the period after the Contract Date within which the Contractor submits a first programme for acceptance is three weeks. The interval for submitting revised programmes and the assessment interval are both a calendar month. The starting date is
March The period for reply is one week.The following are dates on which programmes were submitted by the Contractor and the Project Manager's response. Programme No Contractor's submission Project Manager's response
April
May
Accepted
June
June
Accepted
June
July
Accepted
July
August
Not Accepted
August
September
Accepted On
June the Contractor notifies an early warning. On the
July the Contractor notifies the Project Manager of a compensation event for the same matter notified in the early warning. The Project Manager replies to the Contractor on
July and accepts the event is a compensation event and instructs the Contractor to submit a quotation. The period within which the Contractor submits its quotation is extended and it is submitted on
September
Which programme should be used for assessing the compensation event? Select ONE option.
a None of the programmes should be used. The Project Manager should be making its own assessment of the compensation event.
b Programme No April
c Programme No June
d Programme No June
e Programme No August
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock