Question: A new school is being constructed using the NEC 4 Engineering and Construction Contract Option A with secondary Options X 7 , X 8 ,

A new school is being constructed using the NEC4 Engineering and Construction Contract Option A with secondary Options X7, X8, X16 and X21. No programme is identified in the Contract Data and the period after the Contract Date within which the Contractor submits a first programme for acceptance is three weeks. The interval for submitting revised programmes and the assessment interval are both a calendar month. The starting date is 01 March. The period for reply is one week.The following are dates on which programmes were submitted by the Contractor and the Project Manager's response.
Programme No
Contractor's submission
Project Manager's response
03
30 April
7 May - Accepted
04
01 June
14 June - Accepted
05
30 June
10 July - Accepted
06
31 July
09 August - Not Accepted
07
31 August
05 September - Accepted
On 01 June the Contractor notifies an early warning. On the 07 July, the Contractor notifies the Project Manager of a compensation event for the same matter notified in the early warning. The Project Manager replies to the Contractor on 14 July and accepts the event is a compensation event and instructs the Contractor to submit a quotation. The period within which the Contractor submits its quotation is extended and it is submitted on 07 September. Which programme should be used for assessing the compensation event?
Select ONE option.
None of the programmes should be used. The Project Manager should be making its own assessment of the compensation event.
Programme No 03-30 April.
Programme No 04-01 June.
Programme No 05-30 June.
Programme No 07-31 August.
 A new school is being constructed using the NEC4 Engineering and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!