Question: A new school is being constructed using the NEC 4 Engineering and Construction Contract Option A with secondary Options X 7 , X 8 ,
A new school is being constructed using the NEC Engineering and Construction Contract Option A with secondary Options X X X and X No programme is identified in the Contract Data and the period after the Contract Date within which the Contractor submits a first programme for acceptance is three weeks. The interval for submitting revised programmes and the assessment interval are both a calendar month. The starting date is March. The period for reply is one week.The following are dates on which programmes were submitted by the Contractor and the Project Manager's response.
Programme No
Contractor's submission
Project Manager's response
April
May Accepted
June
June Accepted
June
July Accepted
July
August Not Accepted
August
September Accepted
On June the Contractor notifies an early warning. On the July, the Contractor notifies the Project Manager of a compensation event for the same matter notified in the early warning. The Project Manager replies to the Contractor on July and accepts the event is a compensation event and instructs the Contractor to submit a quotation. The period within which the Contractor submits its quotation is extended and it is submitted on September. Which programme should be used for assessing the compensation event?
Select ONE option.
None of the programmes should be used. The Project Manager should be making its own assessment of the compensation event.
Programme No April.
Programme No June.
Programme No June.
Programme No August.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock