A new surgical facility called Cut & Sew is opening in neighborhoods throughout the United States. They are job shops that handle a variety of outpatient surgical procedures. They set their process up so that one doctor cuts, and the other sews. They have five patients to sequence for tomorrow. Since the weather forecast is for a cool, and sunny day, they would also like to play golf tomorrow. They want to sequence their patients with the objective of minimizing the time from the beginning of the first job until the finish of the last job. The patients and estimated times are as follows: Patient Cut Time (hours) Sew Time (hours) A 2.3 2.8 B 2.5 3.0 C 2.0 1.5 D 0.6 1.0 E 3.6 2.6 Sequence the patients using Johnson's method, state the schedule for each operation, and determine the minimum makespan.