Question: MBA 5 1 2 Homework Assignment H 3 - B Chapter 1 3 - Resource Management Enter Student Name: PROBLEM # 5 A new

MBA 512 Homework Assignment H3-B
Chapter 13- Resource Management
Enter Student Name:
PROBLEM #5
" A new surgical facility called Cut & Sew is opening in neighborhoods throughout the United States.
They are job shops that handle a variety of outpatient surgical procedures. Their process is set up so
that one doctor cuts and the other sews. They have five patients to sequence for tomorrow. Since the
weather forecast is for a cool and sunny day, they would also like to play golf tomorrow. They want to
sequence their patients with the objective of minimizing the time from the beginning of the first job
until the finish of the last job. The patients and estimated times are as follows:
Patient Cut Time (hours) Sew Time (hours)
"
Patient Cut Time (hours) Sew Time (hours)
A 2.32.8
B 2.53.0
C 2.01.5
D 0.61.0
E 3.62.6
ANSWER (You must show all formulas, calculations, and "highlight" corrrect Answers)
a. Sequence the patients using Johnsons method..state the schedule for each operation
b. Determine the minimum Makespan.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!