Question: MBA 5 1 2 Homework Assignment H 3 - B Chapter 1 3 - Resource Management Enter Student Name: PROBLEM # 5 A new
MBA Homework Assignment HB
Chapter Resource Management
Enter Student Name:
PROBLEM #
A new surgical facility called Cut & Sew is opening in neighborhoods throughout the United States.
They are job shops that handle a variety of outpatient surgical procedures. Their process is set up so
that one doctor cuts and the other sews. They have five patients to sequence for tomorrow. Since the
weather forecast is for a cool and sunny day, they would also like to play golf tomorrow. They want to
sequence their patients with the objective of minimizing the time from the beginning of the first job
until the finish of the last job. The patients and estimated times are as follows:
Patient Cut Time hours Sew Time hours
Patient Cut Time hours Sew Time hours
A
B
C
D
E
ANSWER You must show all formulas, calculations, and "highlight" corrrect Answers
a Sequence the patients using Johnsons method..state the schedule for each operation
b Determine the minimum Makespan.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock