Question: A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement
A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change. What should the project manager do? Coach the new team member to conduct the testing the way it has always been done for this project. Ask the new team member to focus only on development and not do the testing. Schedule a meeting with the new team member to learn about the new method of testing Request that the new team member do the testing the way it has always been done for this project
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock