Question: A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement
A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change. What should the project manager do? Request that the new team member do the testing the way it has always been done for this project. Coach the new team member to conduct the testing the way it has always been done for this project. Schedule a meeting with the new team member to learn about the new method of testing. Ask the new team member to focus only on development and not do the testing