Question: A normal 40 hour work week, what would be the $/sfca? Labor Cost Rate Qty Trade ($/mhr) 1 Foreman 20.12 3 Carpenter 18.95 3 Helper
A normal 40 hour work week, what would be the $/sfca?

Labor Cost Rate Qty Trade ($/mhr) 1 Foreman 20.12 3 Carpenter 18.95 3 Helper 14.32 Crew Time (mhr) Per 100 SFCA Item First Use Reuse Fabrication 7.5 Erect & Strip 4.5 6.5 Clean & Move 2.1 1.5 Material Cost Per 100 SFCA Unit First Price Use Reuses $/Mbf Qty (bft) Qty (bft) Plyform 720.00 110.00 11.00 Lumber 530.00 140.00 14.00 Accessories 22.60 Based on one use, the bare cost of labor ($/SFCA) is closest to
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts