Question: Assume a normal 40-hr work schedule and use the data given to answer this question Labor Cost Qty Trade Rate ($/mhr) 1 Foreman 20.12 3
Assume a normal 40-hr work schedule and use the data given to answer this question
| Labor Cost | ||
| Qty | Trade | Rate ($/mhr) |
| 1 | Foreman | 20.12 |
| 3 | Carpenter | 18.95 |
| 3 | Helper | 14.32 |
| Crew Time (mhr) Per 100 SFCA | ||
| Item | First Use | Reuse |
| Fabrication | 7.5 | 1 |
| Erect & Strip | 4.5 | 6.5 |
| Clean & Move | 2.1 | 1.5 |
| Material Cost Per 100 SFCA | |||
|
| Unit Price | First Use | Reuses |
|
| $/Mbf | Qty (bft) | Qty (bft) |
| Plyform | 720.00 | 110.00 | 11.00 |
| Lumber | 530.00 | 140.00 | 14.00 |
Based on seven uses, the bare cost of labor ($/SFCA) is closest to:
12.18
9.74
7.33
4.98
3.12
1.67
You Answered
0.99
0.84
i think 1.67 is the correct answer