Question: Assume a normal 40-hr work schedule and use the data given to answer this question Labor Cost Qty Trade Rate ($/mhr) 1 Foreman 20.12 3

Assume a normal 40-hr work schedule and use the data given to answer this question

Labor Cost

Qty

Trade

Rate ($/mhr)

1

Foreman

20.12

3

Carpenter

18.95

3

Helper

14.32

Crew Time (mhr) Per 100 SFCA

Item

First Use

Reuse

Fabrication

7.5

1

Erect & Strip

4.5

6.5

Clean & Move

2.1

1.5

Material Cost Per 100 SFCA

Unit Price

First Use

Reuses

$/Mbf

Qty (bft)

Qty (bft)

Plyform

720.00

110.00

11.00

Lumber

530.00

140.00

14.00

Based on seven uses, the bare cost of labor ($/SFCA) is closest to:

12.18

9.74

7.33

4.98

3.12

1.67

You Answered

0.99

0.84

i think 1.67 is the correct answer

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!