Question: A part requires three processing steps on two machines in the sequence A-B-B. The demand for this part is 30,000 units per week. The company

A part requires three processing steps on two

A part requires three processing steps on two machines in the sequence A-B-B. The demand for this part is 30,000 units per week. The company operates six days per week, 24 hours per day, and the company performing maintenance activities for all machines for three hours daily. Given the following performance data. Operation Machine Standard Time Efficiency Reliability Defects 1 A 3 min 95% 92% 4% 2 B 1 min 94% 91% 6% 3 B 2 min 93% 90% 4% Calculate the following (Select the correct answer from the dropdown menue) a- The number of parts to start operation 1 v unit b- The number of parts to start operation 2 = v unit c- The number of parts to start operation 3 = v unit d- The total time of maintenance (for 4 weeks) e-The amount of available time = v min f- The number of machines required for operation 1 v machine g- The number of machines required for operation 2 = v machine v machine h- The number of machines required for operation 3 = i- The total number of machine A required for production j- The total number of machine B required for production v machine v machine

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!