Question: A partial information about a project is shown below. Activities G and T must be completed before activity C can start. Activities G, T, and

A partial information about a project is shown
A partial information about a project is shown below. Activities G and T must be completed before activity C can start. Activities G, T, and N must be completed before activity M can start Activities C and M must be completed before activity D can start Activity M must be complete before activity A can start. The duration of activities G, T, N are 16, 22, and 18 days, respectively. The duration of activities C, Mare 23, and 48 days, respectively. Furthermore ES(G) = 26, ES(T) = 25, and ES(N) = 21. Find the value of ES(D)